How to Implement a Design System for a 350-component Vue app in 18 business days
Our company (Flyle, Inc.) implemented a design system in a very short time frame of 18 business days. We will share our findings from this project.
Technical Ingenuity
- Automatically migrate as much as possible in advance using AST, and automatically add TODO comments to all parts that cannot be identified.
- Implemented ESLint custom rules to automate as much of the review as possible.
- Perform VRT to ensure that the design system is not broken.
- E2E testing with Autify
Project Management
- Focus on short term manual work to reduce task switching costs to zero
- Progress is managed numerically
- Multiple manual tests to deal with bugs
- Finally, pair-processing with designers to make minor design changes
Reflection and learning through the project
- We should have understood the detailed dependencies of components in advance (we saw cases where conflicts occurred)
- Mistakes in the migration itself
First, after sharing the above, I would like to devote time to sharing the method of program modification by AST for the first technical innovation point.